GENERAL CONSTRUCTION WORKS IN THE SEMYTSVIT Residential Complex AS OF 05.05.2021

12/05/2021

GENERAL CONSTRUCTION WORKS IN THE SEMYTSVIT Residential Complex AS OF 05.05.2021:
House 15
Monolithic frame - 70% (vertical work is performed
structures of the 10th floor)
Walls - 20% (work is being done on the 4th and 5th floor)

House 17
Walls and partitions - 60%
Internal engineering networks:
- water supply and sewerage - 20%
- heating - 5%
- power grids - 15%
- fire protection systems - 20%
- low-current networks -15%
Filling slots:
- windows - 20%
Filling slots:
- plaster - 15%

House 18
Internal engineering networks:
- water supply heating and sewerage - 95%
- electrical networks and switchboard equipment - 85%
- fire protection systems - 95%
- elevators - 100%
Interior decoration:
- finishing with tiles - 70%
- decoration of walls and ceilings - 50%
Facades - 45%
Metal protections:
- fencing of stairways - 60%
Landscaping - 15% (works are being carried out in the area between houses №18 and №6 and №7)

Another news

arrow-left
arrow-right
LEAVE APPLICATION

CONTACTS

Central office

Lviv, Staryi Rynok Square, 8
+38 (098) 788 11 88
+38 (032) 297 11 61
sales@intergal-bud.com.ua

Sales department

Lviv, st. Shevchenko, 60
+38 (098) 788 11 88
+38 (032) 297 11 61

Order call
Thank you for your inquiry

Our manager will call within 15 minutes

LEAVE APPLICATION
Thank you for your inquiry

Our manager will contact you within 15 minutes and will provide you with detailed information about the apartment of your choice