All construction work on house №17 has been completed.
As of the beginning of January, the following general construction works were performed on the house №15:
1. Earthworks - 100%
2. Arrangement of the pile field and foundations - 100%
3. Monolithic frame - 100%
4. Walls and partitions - 100%
5. Internal engineering networks:
- water supply and sewerage - 90%
- heating - 95%
- power grids - 80%
- fire protection systems - 90%
- low-current networks - 90%
6. Filling of apertures (windows, doors, hatches) - 100%
7. Elevators - 100%
8. Roof - 100%
9. Facades - 80%
10. Finishing:
- plaster and screed - 100%
- finishing of walls and ceilings - 60%
- tiling of floors - 30%
- fencing - 80%
11. External electricity supply, gas supply, water supply and sewerage - 100%