As of the beginning of February, the following general construction works were carried out on house №15:
Earthworks - 100%
Pile field arrangement and foundations - 100%
Monolithic frame - 100%
Walls and partitions - 100%
Internal engineering networks:
- water supply and sewerage - 95%
- heating - 100%
- gas supply - 100%
- power grids - 90%
- fire protection systems - 95%
- low-current networks - 95%
Filling of apertures (windows, doors, hatches) - 100%
Elevators - 100%
Roof - 100%
Facades - 85%
Decoration:
- plaster and screed - 100%
- decoration of walls and ceilings - 85%
- tiling of floors - 90%
- fencing - 90%
External electricity supply, gas supply, water supply and sewerage - 100%