ouse №17
1. Retaining wall, foundations and monolithic frame - 100%
2. Walls and partitions - 100%
3. Internal engineering networks:
- Heating, water supply and sewerage - 100%
- electrical networks and switchboard equipment - 95%
- fire protection systems and low-current networks - 100%
- internal gas supply - 90%
4. Filling of slots - 100%
5. Finishing:
- plaster and screed - 100%
- decoration of walls and ceilings - 97%
- tiling of floors - 95%
- fencing - 95%
6. Elevators - 100%
7. Roof - 100%
8. Facades - 95%
9. External electricity supply, gas supply, water supply and sewerage - 100% (completed);
10. Landscaping:
- paving, side stones and curbs - 70%
- strengthening of slopes with gabions - 100%
11. Landscaping - 40%
12. Cleaning of premises of MZK of the house - 10%
House№15
1. Earthworks - 100%
2. Foundations - 100%
3. Monolithic frame - 100%
4. Walls and partitions - 100%
5. Internal engineering networks:
- water supply and sewerage - 85%
- heating - 80%
- power grids - 70%
- fire protection systems - 80%
- low-current networks - 80%
6. Filling the slots:
- windows, doors - 100%
- technical doors - 90%
7. Elevators - 100%
8. Roof - 100%
9. Facades - 70%
10. Finishing:
- plaster and screed - 100%
- decoration of walls and ceilings - 30%
- fencing - 70%
11. External electricity supply, gas supply, water supply and sewerage - 100%