08/12/2021

ouse №17
1. Retaining wall, foundations and monolithic frame - 100%
2. Walls and partitions - 100%
3. Internal engineering networks:
- Heating, water supply and sewerage - 100%
- electrical networks and switchboard equipment - 95%
- fire protection systems and low-current networks - 100%
- internal gas supply - 90%
4. Filling of slots - 100%
5. Finishing:
- plaster and screed - 100%
- decoration of walls and ceilings - 97%
- tiling of floors - 95%
- fencing - 95%
6. Elevators - 100%
7. Roof - 100%
8. Facades - 95%
9. External electricity supply, gas supply, water supply and sewerage - 100% (completed);
10. Landscaping:
- paving, side stones and curbs - 70%
- strengthening of slopes with gabions - 100%
11. Landscaping - 40%
12. Cleaning of premises of MZK of the house - 10%
House№15
1. Earthworks - 100%
2. Foundations - 100%
3. Monolithic frame - 100%
4. Walls and partitions - 100%
5. Internal engineering networks:
- water supply and sewerage - 85%
- heating - 80%
- power grids - 70%
- fire protection systems - 80%
- low-current networks - 80%
6. Filling the slots:
- windows, doors - 100%
- technical doors - 90%
7. Elevators - 100%
8. Roof - 100%
9. Facades - 70%
10. Finishing:
- plaster and screed - 100%
- decoration of walls and ceilings - 30%
- fencing - 70%
11. External electricity supply, gas supply, water supply and sewerage - 100%

Another news

arrow-left
arrow-right
LEAVE APPLICATION

CONTACTS

Central office

Lviv, Staryi Rynok Square, 8
+38 (098) 788 11 88
+38 (032) 297 11 61
sales@intergal-bud.com.ua

Sales department

Lviv, st. Shevchenko, 60
+38 (098) 788 11 88
+38 (032) 297 11 61

Order call
Thank you for your inquiry

Our manager will call within 15 minutes

LEAVE APPLICATION
Thank you for your inquiry

Our manager will contact you within 15 minutes and will provide you with detailed information about the apartment of your choice