GENERAL CONSTRUCTION WORKS IN "SEMYTSVIT" RESIDENTIAL AS OF 02.04.2021
House №15
Monolithic frame - 45% (work has begun on the floor slab at the floor mark of the 7th floor)
Walls - 5% (work is performed on the 1st floor)
House №17
Monolithic frame - 85%;
Walls and partitions - 35%;
Internal engineering networks:
- prefabricated ventilation ducts and smoke removal system -50%
- water supply and sewerage - 10%;
- fire extinguishing systems - 10%;
- power supply systems -5%;
Window constructions - 1%
House №18
Internal engineering networks:
- water supply and sewerage - 85%;
- heating - 85% (installation of radiators and boilers started);
- power grids - 80%;
- gas supply - 5%;
- fire protection systems - 85%;
- low-current networks - 85%;
- elevators - 100%
Filling the slots
- windows - 100%;
- facade glazing - 100%;
- apartment doors - 80%
- metal and m / n doors - 40%
Interior decoration
- plaster - 95%;
- screeds - 90%
- MZK decoration - 10%
Facades - 15%;
Metal protections
- balcony fencing - 80%