GENERAL CONSTRUCTION WORKS IN "SEMYTSVIT" RESIDENTIAL AS OF 01.06.2021

18/06/2021

House 15
Monolithic frame - 85% (vertical work is performed
structures of the 13th floor)
Walls - 30% (works on internal walls of the 3rd and 4th floors are completed and works on external walls from the 5th to the 7th floor are performed)
Windows - 5% (windows are installed on the 3rd floor)

House 17
Walls and partitions - 75%;
Internal engineering networks:
- water supply and sewerage - 40%;
- heating - 20%;
- power grids - 35%;
- fire protection systems - 35%;
- low-current networks -35%
Filling slots:
- windows - 65%
Decoration:
- plaster - 60%;
- screed - 10%

House 18
Internal engineering networks:
- heating, water supply and sewerage - 95%;
- water meter unit and pumping station - 100%;
- power grids and switchboard equipment - 90%;
- fire protection systems - 95%;
- low-current networks and elevators - 100%;
Filling of openings (windows, front glazing, apartment,doors) - 100%;
Interior decoration:
- plaster and screeds - 100%;
- finishing with tiles - 90%;
- decoration of walls and ceilings - 85%;
The roof of the house - 100%;
Ebbs and covers of parapets - 30%
Facades - 75%;
Metal protections:
- fencing of balconies - 100%;
- fencing of stairways - 80%
- fencing of stylobates and retaining walls - 50%
External networks  - 100%
- electricity, water supply and sewerage - 100%;
- gas supply - 80%
Landscaping - 50%

Another news

arrow-left
arrow-right
LEAVE APPLICATION

CONTACTS

Central office

Lviv, Staryi Rynok Square, 8
+38 (098) 788 11 88
+38 (032) 297 11 61
sales@intergal-bud.com.ua

Sales department

Lviv, st. Shevchenko, 60
+38 (098) 788 11 88
+38 (032) 297 11 61

Order call
Thank you for your inquiry

Our manager will call within 15 minutes

LEAVE APPLICATION
Thank you for your inquiry

Our manager will contact you within 15 minutes and will provide you with detailed information about the apartment of your choice